First Foundation Walls At Aspen

>> Monday, May 18, 2009



The first foundation walls were poured today at the Aspen Drive Library!

Despite the rain, the construction crew at EVS is still on schedule. So far, the crew has dug a detention pond, created a clay building pad, dug concrete footings, and started pouring concrete for the foundation walls. The building is on track to be completed in April, 2010.

For more construction photos, click here.

0 comments:

  © Blogger templates Palm by Ourblogtemplates.com 2008

Back to TOP